DAN RIVER: Records: Duke warned about pipe that caused spill - WRBL

Records: Duke warned about pipe that caused spill

Posted: Updated:
Duke Energy's Dan River Steam Station in Eden, N.C. Duke Energy's Dan River Steam Station in Eden, N.C.
  • Coal Ash SpillMore>>

  • Environment group says public 'mislead' to think Dan River is clean

    Environment group says public 'mislead' to think Dan River is clean

    Friday, July 18 2014 2:06 PM EDT2014-07-18 18:06:07 GMT
    Waterkeeper Alliance says photos show coal ash is still present in the Dan River. (Waterkeeper Alliance)Waterkeeper Alliance says photos show coal ash is still present in the Dan River. (Waterkeeper Alliance)
    Waterkeeper Alliance provided photos it says show deposits of coal ash still in the Dan River despite claims to the contrary.
    Waterkeeper Alliance provided photos it says show deposits of coal ash still in the Dan River despite claims to the contrary.
  • NC, Va. groups to monitor coal ash in Dan River

    NC, Va. groups to monitor coal ash in Dan River

    Friday, July 18 2014 9:59 AM EDT2014-07-18 13:59:45 GMT
    A collapsed pipe at Duke Energy's Dan River Steam Station dumped coal ash into the Dan River.A collapsed pipe at Duke Energy's Dan River Steam Station dumped coal ash into the Dan River.
    Two water protection groups will continue to monitor the Dan River to identify coal ash from a massive spill in North Carolina that flowed into Virginia.
    Two water protection groups will continue to monitor the Dan River to identify coal ash from a massive spill in North Carolina that flowed into Virginia.
  • Feds: Duke Energy has finished moving coal ash from Dan River

    Feds: Duke Energy has finished moving coal ash from Dan River

    Thursday, July 17 2014 3:03 PM EDT2014-07-17 19:03:48 GMT
    Duke has dredged up about 2,500 tons of ash and contaminated sediment, as well as another 500 tons that had accumulated in settling tanks at downstream municipal water treatment plants.
    Duke has dredged up about 2,500 tons of ash and contaminated sediment, as well as another 500 tons that had accumulated in settling tanks at downstream municipal water treatment plants.
RALEIGH, N.C. -

Records subpoenaed by federal prosecutors show engineers working for Duke Energy warned the company nearly 30 years before a massive coal ash spill that a stormwater pipe running under an ash dump was made of corrugated metal and needed to be monitored for leaks.

That pipe at a North Carolina dump collapsed in February, triggering a spill that coated 70 miles of the Dan River in toxic gray sludge. Following the disaster, Duke officials said the company didn't know that an underground section of the pipe was made out of metal, believing instead that it had been fully constructed of more-durable reinforced concrete.

Duke spokesman Dave Scanzoni declined to comment Thursday about the documents or whether the company implemented the monitoring recommended by its engineers.

The 28-year-old engineering report was among documents subpoenaed last week from the N.C. Utilities Commission by the U.S. Attorney in Raleigh as part of an ongoing grand jury investigation into the spill. The Associated Press filed a public records request with the state agency, which was responsible for regulating Duke's 33 coal ash pits in North Carolina up until 2010.

Starting in the mid-1970s, the commission mandated Duke to submit independent engineering studies every five years affirming the safety of the huge earthen dikes holding back millions of tons of ash and contaminated water from nearby rivers and lakes.

Coal ash is the byproduct left behind when coal is burned to generate energy. It contains numerous toxic substances, including arsenic, selenium, chromium, beryllium, thallium, mercury, cadmium and lead. Some of the chemicals in wet ash can also corrode metal.

Duke hired Law Engineering Testing Co. to perform the required inspections at the Dan River Steam Station in Eden. In its 1986 report, the Charlotte firm noted that part of the pipe was made of metal.

"Part of this culvert is constructed of corrugated metal pipe which would be expected to have less longevity of satisfactory service than the reinforced concrete pipes," the report states.

Among the eight recommendations made at the end of the 45-page report, the engineers specifically suggest Duke check on the pipe under the coal ash dump at least every six months. The report said the inside of the pipes should be checked for leaks anytime there was a significant difference between how much was flowing in and how much was flowing out.

In the days after the Feb. 2 spill, Duke issued public statements expressing surprise that the pipe wasn't made of corrosion-resistant concrete.

"Originally, the media reported and we reported that this was a concrete pipe, the 48-inch one, because what we could see is right here at the river," Duke's lead lobbyist, George Everett, told state lawmakers at a Feb. 17 oversight hearing into the spill. "The rest of this pipe, we discovered, as we worked from the other end, is a metal pipe — asphalt-coated metal corrugated pipe. That's the piece ... that broke."

On Monday, North Carolina regulators cited Duke for leaking pipes under coal ash dumps at five of its plants, some of them constructed from old corrugated metal. Duke said it is working to fix the leaks.

The 1986 study from the Dan River plant also makes numerous references to a prior 1981 review that found problems at the Eden coal ash dump. It is not clear if that earlier report also warned about the metal pipe.

Sam Watson, spokesman for the utility commission, says there is no record that Duke ever submitted that 1981 engineering report to state regulators, as required.

Scanzoni, the Duke spokesman, said Thursday the company still has a copy, though he declined to share it with The Associated Press.

Copyright 2014 The Associated Press. All rights reserved.

  • Trending StoriesTrending StoriesMore>>

  • Teen mom charged after baby found buried at Louisburg home

    Teen mom charged after baby found buried at Louisburg home

    Tuesday, July 22 2014 11:44 PM EDT2014-07-23 03:44:25 GMT
    Ashley Reed, 16, of Louisburg is charged with concealing a death after her infant was found buried beside her house.
    Ashley Reed, 16, of Louisburg is charged with concealing a death after her infant was found buried beside her house.
  • Largest companies by revenue in each state

    Largest companies by revenue in each state

    Thursday, July 10 2014 8:01 PM EDT2014-07-11 00:01:10 GMT
    Broadview Networks recently decided to find out the biggest -- by revenue -- company in each state in the US.The company used the Fortune 500 list to start with, but needed data by state, so it turned to Hoover's.With data from that company, they were able to search through each state's list of companies and then find the largest -- by revenue.Just flip through the list above and see who is the biggest in each state, what town they are based and their revenue.
    Broadview Networks recently decided to find out the biggest -- by revenue -- company in each state in the US.The company used the Fortune 500 list to start with, but needed data by state, so it turned to Hoover's.With data from that company, they were able to search through each state's list of companies and then find the largest -- by revenue.Just flip through the list above and see who is the biggest in each state, what town they are based and their revenue.
  • Couple arrested for having sex on Cortez Beach in front of beachgoers

    Couple arrested for having sex on Cortez Beach in front of beachgoers

    Tuesday, July 22 2014 1:08 PM EDT2014-07-22 17:08:35 GMT
    Bradenton Beach police officers were dispatched to Cortez Beach after a few people called 911 and complained about a couple having sex publicly, right next to a little girl on the beach.
    Bradenton Beach police officers were dispatched to Cortez Beach after a few people called 911 and complained about a couple having sex publicly, right next to a little girl on the beach.
Powered by WorldNow

1350 13th Avenue
Columbus, GA 31901

Telephone: 706.323.3333
Fax: 706.327.6655
Email: news@wrbl.com

Can't find something?
Powered by WorldNow
All content © Copyright 2000 - 2014 Media General Communications Holdings, LLC. A Media General Company.